Visited the site last Saturday to meet with the Electrical contractor only to be disappointed with what I saw - what they said that should have been fixed is still the same as a 1.5months ago.
But what's worse is that the contractor forgot about the sarking we have included in one of the amendments to our plans. It is part of the Basix report and we had added it despite of the cost for its additional benefit. I still don't know what will happen next but we really want those sarking installed.
I called the builder today and the customer service personnel is checking on it with the site supervisor. Even before this happened, I already requested that I inspect the property but I have not heard from them a schedule.
we call it Tahanan, a filipino word that means a house or home. A place to be at ease and feel the love of the family. Tahanan comes from the root word 'tahan' which means cessation of the crying or abolition of grief. It is said that your sadness goes away when you are in your own home.
Home Building 101
Our first home building adventure.
Tahanan Time Line
All about the land
Land Settlement (11-May-2009)
Land Title Transferred (25-June-2009)
Construction
Free quotation / Initial Tender
Security Payment
1st Draft of Drawing
2nd Draft of Drawing
Hydraulic Plan
Colour Selection
Final Drawing for Approval
Revision Requested by Certifier
Revised Drawing
Approved Plans via private certifier (24-March-2010)
Final Contract Review / Signing (21-April-2010)
Tree Removal (1-May-2010)
Submission of Letter to Commence Construction (9-May-2010)
Security Payment
1st Draft of Drawing
2nd Draft of Drawing
Hydraulic Plan
Colour Selection
Final Drawing for Approval
Revision Requested by Certifier
Revised Drawing
Approved Plans via private certifier (24-March-2010)
Final Contract Review / Signing (21-April-2010)
Tree Removal (1-May-2010)
Submission of Letter to Commence Construction (9-May-2010)
Drawings Revision Required (22-29 May 2010)
Rev2 drawings sent to the Private Certifier (24-June-2010)
2nd revision of the plan approved by Private Certifier (30-June-2010)
Day 1 - Construction (11-June-2010 ??, within 28 days) - 12-July-2010
Piering - 28-July-2010
Slab - 16-August-2010
Frame - 23-Sept-2010
Day 1 - Construction (11-June-2010 ??, within 28 days) - 12-July-2010
Piering - 28-July-2010
Slab - 16-August-2010
Frame - 23-Sept-2010
Brickwork - 10-Nov-2010
Roof Tiles - 12-Nov-2010
Lock Up - 16-Feb-2011
Fixing Out -4-March-2011
Painting - 8-April-2011
Lock Up - 16-Feb-2011
Fixing Out -4-March-2011
Painting - 8-April-2011
Final Inspection 13-April-2011
Completion -
Handover -
Move-in -
Monday, November 22, 2010
Friday, November 19, 2010
Rush Time
This week is both exciting and stressful as we had to finalize the electrical and the A/C location and stuff.
We finalized the upgrades to the electrical...
The Aircon location was also reviewed and had to made quick decisions since the blokes were already installing it.
We got the quotes for the landscapes.. and we gotta look for alternatives... and see if the quotes are reasonable. :)
We finalized the upgrades to the electrical...
- Downlights to the common areas - wiring and getting it ready with the installation of downlights.
- Two sets of powerpoints per room
- Data cabling
- External lightings
- Aerial antenna to get the HD channels.
The Aircon location was also reviewed and had to made quick decisions since the blokes were already installing it.
We got the quotes for the landscapes.. and we gotta look for alternatives... and see if the quotes are reasonable. :)
Tuesday, November 16, 2010
Bricks and Roof Tiles
Last week was a good week for progress.
The bricks were completed, then on Thursday we saw the roof tiles delivered around 9am.
I thought that probably middle of this week it will be completed. Then when we visited the site last Saturday this is what we saw - a red roof!
It looks like it is completed since most of the Finally I get to see how the brick and roof tile combo would look like and I couldn't be happier with what we chose. We wanted to be a little different with our neighbors and yet a bit conservative in colour.
The bricks were completed, then on Thursday we saw the roof tiles delivered around 9am.
I thought that probably middle of this week it will be completed. Then when we visited the site last Saturday this is what we saw - a red roof!
It looks like it is completed since most of the Finally I get to see how the brick and roof tile combo would look like and I couldn't be happier with what we chose. We wanted to be a little different with our neighbors and yet a bit conservative in colour.
Thursday, September 23, 2010
Frames Up!
Yesterday I went to the site to visit the progress and was happy to see all of the wall frames has been set up. Then today, I got a progress update from the Customer Service of the builder that the roof trusses has been completed yesterday afternoon. That excited me since it is nicer to see physical progress rather than exchanges in plans and emails. Now here comes the 2nd progress payment.
Things ticked off the list:
1. Finalized with the tiler the changes we wanted to do. Paid them and the invoice has been received.
2. Finalized the A/C to be installed in the house - Actron ESP+, supposedly more energy efficient since you are able to control the temperature and fan speed. Hopefully the slight investment is worth the extra cost we spent.
3. Received the FHOG and now the balance has been deposited on the MISA account.
4. Received an invoice from the builder that the water connection has been completed.
Things needed to work on:
1. Finalize tiles / flooring - November
2. Finalize the supplier for the downlights - early October
3. Finalize the electrical upgrades - early October
4. Finalize the landscape cost - retaining walls, driveways, etc.. - November
Things ticked off the list:
1. Finalized with the tiler the changes we wanted to do. Paid them and the invoice has been received.
2. Finalized the A/C to be installed in the house - Actron ESP+, supposedly more energy efficient since you are able to control the temperature and fan speed. Hopefully the slight investment is worth the extra cost we spent.
3. Received the FHOG and now the balance has been deposited on the MISA account.
4. Received an invoice from the builder that the water connection has been completed.
Things needed to work on:
1. Finalize tiles / flooring - November
2. Finalize the supplier for the downlights - early October
3. Finalize the electrical upgrades - early October
4. Finalize the landscape cost - retaining walls, driveways, etc.. - November
Saturday, August 28, 2010
Quiet Time
The last two weeks has been quiet time with the builder. Two weeks ago, they poured the slab and it takes about 1week to really cure and another week waiting for the delivery of the frames.
It has been a bit busy on the finance side as we were taking care of the 1st progress payment but found some roadblock with the bank. Hopefully it does not lead to further delays.
We filed for an extension on the FHOG. We submitted 2 letters for the extension - one from us, and another from the builder. Still praying that we get the full amount. I will be sad if we miss it.
We also met with the landscape supplier now we are able to visualize the requirement and what can be done to minimize the cost. We plan to have a deck but still not finalized.
On the electrical contractor - we more or less agree on the A/C to get... the Actron ESP+. On the lighting... we have not finalized it yet but when I visited Beacon Lighting... it did help talking to someone to understand the different downlights.
It has been a bit busy on the finance side as we were taking care of the 1st progress payment but found some roadblock with the bank. Hopefully it does not lead to further delays.
We filed for an extension on the FHOG. We submitted 2 letters for the extension - one from us, and another from the builder. Still praying that we get the full amount. I will be sad if we miss it.
We also met with the landscape supplier now we are able to visualize the requirement and what can be done to minimize the cost. We plan to have a deck but still not finalized.
On the electrical contractor - we more or less agree on the A/C to get... the Actron ESP+. On the lighting... we have not finalized it yet but when I visited Beacon Lighting... it did help talking to someone to understand the different downlights.
Wednesday, August 18, 2010
Invoice Received
I just got from the mail the invoice from the builder for the slab being complete It is nice to here that after 1.5 months, the first stage is complete.
I passed by the project site yesterday and I saw the workers working on the site. Probably removing the other stuff they used when they poured the slab last week.
Now where did I put that form from the bank? :)
I passed by the project site yesterday and I saw the workers working on the site. Probably removing the other stuff they used when they poured the slab last week.
Now where did I put that form from the bank? :)
Friday, August 13, 2010
Concreting of the Slab - Scheduled today
I asked my wife to visit the site to see if workers are there. True enough a mixer was on standby. She didn't go down to check further but seeing people working on site is already good news for us since any
rainfall does affect the schedule.
Then this afternoon, I emailed the customer service rep of the builder and she confirmed that today is the day. I asked Joanna to pass by after picking up the kids. Hopefully a few snaps. If not I will be there on-site tomorrow.
Still a lot of things to finalise:
1. Kitchen plans still not finalised with the builder with minor difference of what was discussed with the contractor and what is reflected on the plan.
2. Electrical - still working at finalising the details of the lighting and upgrades we want. Hopefully finalise it within the next week so we can get a new quotation. So far, the pricing for the AC is slightly
better than expected.
3. FHOG application details
4. Landscapes and driveways.
rainfall does affect the schedule.
Then this afternoon, I emailed the customer service rep of the builder and she confirmed that today is the day. I asked Joanna to pass by after picking up the kids. Hopefully a few snaps. If not I will be there on-site tomorrow.
Still a lot of things to finalise:
1. Kitchen plans still not finalised with the builder with minor difference of what was discussed with the contractor and what is reflected on the plan.
2. Electrical - still working at finalising the details of the lighting and upgrades we want. Hopefully finalise it within the next week so we can get a new quotation. So far, the pricing for the AC is slightly
better than expected.
3. FHOG application details
4. Landscapes and driveways.
Wednesday, August 11, 2010
Work continues... post rain fall
Visited the block of land today and saw the trades people hard at
work. One guy said, "I should have prayed harder so the rains would
stop so we can finish the work on the slab". I can't agree more. When
it started to rain yesterday, I knew it was a few steps back from where
they were progressing. Anyway, here we are going to wish for a sunny
week.
work. One guy said, "I should have prayed harder so the rains would
stop so we can finish the work on the slab". I can't agree more. When
it started to rain yesterday, I knew it was a few steps back from where
they were progressing. Anyway, here we are going to wish for a sunny
week.
Tuesday, August 10, 2010
Rainy Day = no work
Since we are in the concreting stage ... i visited the site at 9am today and no work since it has been raining all morning. I did take a few photos of the progress so far.
photos to follow.
photos to follow.
Wednesday, August 4, 2010
Excess Soil Removed... now my pocket hurts
During the morning of 3rd August 2010, the builder called me on my mobile asking me to remove the soil asap so as not to delay the progress on the slab.
She asked that I remove about 50-60 tonnes of dirt. I asked how much that would cost and they patched me through their concrete contractor
to discuss my option. he said it would be about 4-6 truck loads... I said I will go and canvass first and ask my wife.
We agreed on the price - $600/truck, since it was cheaper than what we canvassed and they can do it within the day.
Cost is inclusive of removal (excavator, trucks and tipping to a somewhere else).
Then during lunch time, the contractor contacted me that it looks like it will be 7-8 trucks and wanted me there so I can see for myself. It was a good thing that I was able to leave the office to check it out. True enough the day ended with 8 trucks - paid the contractor $4800 just to throw the excess soil.
We felt so down for several reasons:
1. It was an out of pocket expense and not planned for. 5 grand in one day really hurts the pocket...
2. Putting it in the tender as a provisional allowance would have been easier so it can be part of the loan.
3. They didn't tell us about it before hand. Maybe it was one of those fine lines that we need to read again. Or we expected it but we thought we need to do that prior to moving into the house.
Key learnings:
1. Make sure that removal of excess soil is part of the provisional allowance.
2. Once they start piering, look for a place to dump the dirt, maybe someone looking for additional fill. That should minimize the the cost you have to pay.
3. Leave some dirt so you don't need to get another clean fill when you complete the landscaping later on.
She asked that I remove about 50-60 tonnes of dirt. I asked how much that would cost and they patched me through their concrete contractor
to discuss my option. he said it would be about 4-6 truck loads... I said I will go and canvass first and ask my wife.
We agreed on the price - $600/truck, since it was cheaper than what we canvassed and they can do it within the day.
Cost is inclusive of removal (excavator, trucks and tipping to a somewhere else).
Then during lunch time, the contractor contacted me that it looks like it will be 7-8 trucks and wanted me there so I can see for myself. It was a good thing that I was able to leave the office to check it out. True enough the day ended with 8 trucks - paid the contractor $4800 just to throw the excess soil.
We felt so down for several reasons:
1. It was an out of pocket expense and not planned for. 5 grand in one day really hurts the pocket...
2. Putting it in the tender as a provisional allowance would have been easier so it can be part of the loan.
3. They didn't tell us about it before hand. Maybe it was one of those fine lines that we need to read again. Or we expected it but we thought we need to do that prior to moving into the house.
Key learnings:
1. Make sure that removal of excess soil is part of the provisional allowance.
2. Once they start piering, look for a place to dump the dirt, maybe someone looking for additional fill. That should minimize the the cost you have to pay.
3. Leave some dirt so you don't need to get another clean fill when you complete the landscaping later on.
Monday, July 12, 2010
Work on the land has started!
News! News! News!
July 7 - we were contacted by a representative from the Builder and indicated that she will be the customer representative handling our construction. She also said that she will be in contact with us 1-2x per week to provide progress reports and what needs to be organized. This is actually a very good news as we don't have to be the one to follow up with them. I think in a business perspective, it is also better for them. I hope everything works out well until we complete the construction.
Last Thursday we were advised that the below ground tank will be completed and this week, it will be putting in the fill requirement and leveling the land. Spoke with the Nolan's Quarry and they were requested to deliver 150tonnes (quite good news since it is lower than what we expected). Savings of 800 dollars.
I visited the land yesterday and saw that it has been cut... now I can slightly visualize how high the house will be. since the house on our left and right are 2 level houses.. looks like we are a tad lower than them. Maybe not an issue with us. :)
Things to finish off:
July 7 - we were contacted by a representative from the Builder and indicated that she will be the customer representative handling our construction. She also said that she will be in contact with us 1-2x per week to provide progress reports and what needs to be organized. This is actually a very good news as we don't have to be the one to follow up with them. I think in a business perspective, it is also better for them. I hope everything works out well until we complete the construction.
Last Thursday we were advised that the below ground tank will be completed and this week, it will be putting in the fill requirement and leveling the land. Spoke with the Nolan's Quarry and they were requested to deliver 150tonnes (quite good news since it is lower than what we expected). Savings of 800 dollars.
I visited the land yesterday and saw that it has been cut... now I can slightly visualize how high the house will be. since the house on our left and right are 2 level houses.. looks like we are a tad lower than them. Maybe not an issue with us. :)
Things to finish off:
- Review the final plans that we received last Friday (9th July 2010) and feedback to
- Electrical - will be meeting with the supplier on the 27th to check what we want and how much it would cost us. Hopefully it is just a single meeting and we can proceed.
- FHOG
- Flooring - need to finalise it in August to give us ample time.
Sunday, May 30, 2010
May 22-29 was a wet week
Two weeks ago, someone working on excavation called me to check the block of land. Unfortunately, the rains started to pour down the whole week. So when Monday came, I thought.. one week lost. :(
Some changes had to be done on the block of land. Since our block was higher on the front of the block and for some unfortunate thing, the sewer line runs at the top of the block... so the builder contacted us about an issue. We were a bit alarmed since they said that the president (PR) wanted to talk to us about some issues in the building.
Since our house plan is split level, with the rear part being lower (about 4 steps), they had to raise it so we won't have an issue with the sewer. So we were given a few options:
1. Put in a tank and a pump - costly option, needs council approval, high maintenance cost.
2. Have an additional split, from the front of the house, split it by 2 steps, then another 2 steps to the rear. - ending up with 3 levels. So there will be a 2 steps going to the rumpus and the corridor to Bed 3 and 4.
3. Raise the rear of the house so we end up with 2 levels and the steps is reduced to 2 steps instead of the original 4 steps. - the trade off is we will have a bulkhead at the rear wall, impacting the windows.
So we decided on option 3, which is the cheapest option so far. bulkhead may be the only difference... but i hope our decision is the best one. :)
Impact is that they need to redraw the slab and structural design. maybe 1-2 weeks off the schedule.
Only good thing this week - the security fence has been put up already. :) slowly getting there.
Some changes had to be done on the block of land. Since our block was higher on the front of the block and for some unfortunate thing, the sewer line runs at the top of the block... so the builder contacted us about an issue. We were a bit alarmed since they said that the president (PR) wanted to talk to us about some issues in the building.
Since our house plan is split level, with the rear part being lower (about 4 steps), they had to raise it so we won't have an issue with the sewer. So we were given a few options:
1. Put in a tank and a pump - costly option, needs council approval, high maintenance cost.
2. Have an additional split, from the front of the house, split it by 2 steps, then another 2 steps to the rear. - ending up with 3 levels. So there will be a 2 steps going to the rumpus and the corridor to Bed 3 and 4.
3. Raise the rear of the house so we end up with 2 levels and the steps is reduced to 2 steps instead of the original 4 steps. - the trade off is we will have a bulkhead at the rear wall, impacting the windows.
So we decided on option 3, which is the cheapest option so far. bulkhead may be the only difference... but i hope our decision is the best one. :)
Impact is that they need to redraw the slab and structural design. maybe 1-2 weeks off the schedule.
Only good thing this week - the security fence has been put up already. :) slowly getting there.
Tuesday, May 18, 2010
Rainy Week Ahead
From all the actions last week, with the rains forecasted.. it may be a wet week so far.
As far as chasing people around. Just talked with the broker since I was following up on the FHOG submission.
She said that has to wait until the slab has been laid before she passes the application. I hope no issues occurs because of that. The impact though is that we need to do the advance payment for the first progress payment as this was supposed to come from the 24k FHOG. I guess we should start to expect that so that when the FHOG application is approved, then we have a blessing worth 24k.
Talked also with the builder to close on the questions about the availability of services upto the Right of Way (ROW). No news yet hopefully a good answer will come out of their review.
Friday, May 14, 2010
House Plans
The block of land we bought is a battle axe block. It is called such because of the shape of the block - notice the handle (driveway) then the block forms somewhat of the head of the axe. From the road, I have a long driveway before it reaches our land. It is very common in the area where big blocks of land (bigger than 1000sqm) is subdivided by the current owner to be able to sell it. The house in blue is an existing house in front of our block.

While the waiting game is over and I am in the mood to update the blog. Here is the a snapshot of how the house will sit on the block of land. The trees shown there has been cut down and will be replaced by 4 new trees maybe next year. Since the land is a battle axe block, I needed to provide a turning circle for the vehicle to drive out of the block facing forward. It will be a split level house with the rear being lower by about 3 steps inside the house.
While the waiting game is over and I am in the mood to update the blog. Here is the a snapshot of how the house will sit on the block of land. The trees shown there has been cut down and will be replaced by 4 new trees maybe next year. Since the land is a battle axe block, I needed to provide a turning circle for the vehicle to drive out of the block facing forward. It will be a split level house with the rear being lower by about 3 steps inside the house.
External Colors
I got this photo from the Austral website which shows the bricks we chose for our house. It also more or less use the same shade of red we chose for the roof tiles. Without the second level, this is the external colour that we chose including the fascia and gutters. Hopefully everything turns out well.
This is a sample of how the color combination we thought of. The design is quite different but color of the roof and brick should be close. I think the roof tiles is on the darker side though. Check out the sample below from the website of Bristile Roofing.
Bricks: Austral Moccasin
Roof Tiles: Bristile Redwood
The image below is how the house will look like - front view. With the actual dimensions.
Is this Week1?
Just after sending the letter to the builder, there was some little things happening that indicates that things are already moving ahead.
Some of the silt protection has been set up already.
- Margaret from the builder called to ask about if all the services are available already - funny that she'd ask me when it is for them to tell me what is available and what is not so it can be organized. Anyway, the call ended well that she'll check it out and let me know. For the record:
- Gas connection - I sent an email 2 weeks ago to the person in charge of contracts that I tried to follow up with Jemena but they said that the requestor is the builder so I should coordinate with them. I forwarded it to margaret to help me follow up.
- For the electricity - during the contract signing, they asked me to call a number but ended up that the area is handled by Energy Australia, CC said that they can deal directly with Energy Australia.
- Water - I remember filling up a form for Sydney water. I hope that covers it.
- Someone who does excavations called me up today and he said he will check the land tomorrow (Saturday) and let me know about the fill requirement.
- I was able to check the block of land again today to see the grinding for the tree removal. Looks like everything is ok. Time to pay them up.
- Another surprise is to see the silt protection is up. I guess I can expect some excavations to be done hopefully by next week.
Some of the silt protection has been set up already.
Sunday, May 9, 2010
Trees Removed
Finally, the trees in the land has been removed and the stumps grinded.
In case you are curious to know what trees were removed, they are:
1x angophora floribunda
1x Eucalyptus Saligna
1x Brachyton Acerifolius
1x Michelia Sp
In case you are curious to know what trees were removed, they are:
1x angophora floribunda
1x Eucalyptus Saligna
1x Brachyton Acerifolius
1x Michelia Sp
A productive weekend started this Friday
After several follow-ups with the broker, finally the letter to commence construction has been released. So according to the builder they will start within 28 days from receipt of the letter. I have just sent the letter to the builder and hopefully all goes well.
We also got the trees removed.. including the stumps. Land ready for construction.
Then the builder has forwarded the costing for the kitchen. Although upon discussion with Joanna. Looks like we want to reduce some of the pot drawers.
Hoping all is well with the next few weeks.
Photos to follow. :)
We also got the trees removed.. including the stumps. Land ready for construction.
Then the builder has forwarded the costing for the kitchen. Although upon discussion with Joanna. Looks like we want to reduce some of the pot drawers.
Hoping all is well with the next few weeks.
Photos to follow. :)
Tuesday, May 4, 2010
It is quiet today
No follow ups from the builder.
No news from the broker after sending an email and a call. The decided to call only to find out that she's out for the day. Had to send an email copying the owner as I don't have an idea when she'll be back.
... waiting... how long can one's patience be.. before it is gone?
No news from the broker after sending an email and a call. The decided to call only to find out that she's out for the day. Had to send an email copying the owner as I don't have an idea when she'll be back.
... waiting... how long can one's patience be.. before it is gone?
Monday, May 3, 2010
Still waiting...
On the financing front:
Today we sent off to the broker the details they required for the loan and FHOG. The said that the bank releases the Letter to Commence Construction within 5 business days and today is the 5th day.
On the construction side, we are waiting for the details for the kitchen.. excited to see the plans we wanted... anxious too because we don't have an idea how much it would cost. Carla did mention that this should not delay anything on their part as long as they get the letter from the Bank.
Today we sent off to the broker the details they required for the loan and FHOG. The said that the bank releases the Letter to Commence Construction within 5 business days and today is the 5th day.
On the construction side, we are waiting for the details for the kitchen.. excited to see the plans we wanted... anxious too because we don't have an idea how much it would cost. Carla did mention that this should not delay anything on their part as long as they get the letter from the Bank.
Friday, April 30, 2010
CCC
Today, I got off the phone with the broker, I was informed that the CCC has been revised since the valuation of the house is higher than the loan we wanted. So the LMI has been reduced - that is some good news. The not so good news is that means we still don't have the Letter to Commence Construction.
Friday, April 23, 2010
Passing the ball to the broker/bank
Scanned the documents and submitted the contract to the broker. We were
then informed that it takes 5 business days to get the letter. Now the
countdown begins. Assuming they submit it tomorrow, Friday (23rd), then
we should have a letter by Monday 3rd of May at the latest.
Have a good long weekend.
22 April 2010
then informed that it takes 5 business days to get the letter. Now the
countdown begins. Assuming they submit it tomorrow, Friday (23rd), then
we should have a letter by Monday 3rd of May at the latest.
Have a good long weekend.
22 April 2010
Thursday, April 22, 2010
Building Contract - Signed!
Finally, after the long wait -- we signed our building contract. A
5-day cooling off period has started.
- house plans approved by the private certifier
- colour selections finalized, that means any change we make will be an
addl cost to us if through the builder
- we were given the final contract we can give to the bank so they can
issue us with the Letter to Commence Construction.
only pending area is the kitchen due to the delay in getting the details
from their supplier.
A big leap... and we are happy to do it.
21 April 2010
10am - 1230pm
5-day cooling off period has started.
- house plans approved by the private certifier
- colour selections finalized, that means any change we make will be an
addl cost to us if through the builder
- we were given the final contract we can give to the bank so they can
issue us with the Letter to Commence Construction.
only pending area is the kitchen due to the delay in getting the details
from their supplier.
A big leap... and we are happy to do it.