Home Building 101

Our first home building adventure.

Tahanan Time Line

All about the land

Land auction (28-Mar-2009)
Land Settlement (11-May-2009)
Land Title Transferred (25-June-2009)

Construction
Free quotation / Initial Tender
Security Payment
1st Draft of Drawing
2nd Draft of Drawing
Hydraulic Plan
Colour Selection
Final Drawing for Approval
Revision Requested by Certifier
Revised Drawing
Approved Plans via private certifier (24-March-2010)
Final Contract Review / Signing (21-April-2010)
Tree Removal (1-May-2010)
Submission of Letter to Commence Construction (9-May-2010)
Drawings Revision Required (22-29 May 2010)
Rev2 drawings sent to the Private Certifier (24-June-2010)
2nd revision of the plan approved by Private Certifier (30-June-2010)
Day 1 - Construction (11-June-2010 ??, within 28 days) - 12-July-2010
Piering - 28-July-2010
Slab - 16-August-2010
Frame - 23-Sept-2010
Brickwork - 10-Nov-2010
Roof Tiles - 12-Nov-2010
Lock Up - 16-Feb-2011
Fixing Out -4-March-2011
Painting - 8-April-2011
Final Inspection 13-April-2011
Completion -
Handover -
Move-in -

Friday, November 19, 2010

Rush Time

This week is both exciting and stressful as we had to finalize the electrical and the A/C location and stuff. 

We finalized the upgrades to the electrical...
  1. Downlights to the common areas - wiring and getting it ready with the installation of downlights.
  2. Two sets of powerpoints per room
  3. Data cabling
  4. External lightings
  5. Aerial antenna to get the HD channels.
Hopefully we covered everything

The Aircon location was also reviewed and had to made quick decisions since the blokes were already installing it. 

We got the quotes for the landscapes.. and we gotta look for alternatives... and see if the quotes are reasonable. :)