Tahanan Time Line

All about the land

Land auction (28-Mar-2009)
Land Settlement (11-May-2009)
Land Title Transferred (25-June-2009)

Construction
Free quotation / Initial Tender
Security Payment
1st Draft of Drawing
2nd Draft of Drawing
Hydraulic Plan
Colour Selection
Final Drawing for Approval
Revision Requested by Certifier
Revised Drawing
Approved Plans via private certifier (24-March-2010)
Final Contract Review / Signing (21-April-2010)
Tree Removal (1-May-2010)
Submission of Letter to Commence Construction (9-May-2010)
Drawings Revision Required (22-29 May 2010)
Rev2 drawings sent to the Private Certifier (24-June-2010)
2nd revision of the plan approved by Private Certifier (30-June-2010)
Day 1 - Construction (11-June-2010 ??, within 28 days) - 12-July-2010
Piering - 28-July-2010
Slab - 16-August-2010
Frame - 23-Sept-2010
Brickwork - 10-Nov-2010
Roof Tiles - 12-Nov-2010
Lock Up - 16-Feb-2011
Fixing Out -4-March-2011
Painting - 8-April-2011
Final Inspection 13-April-2011
Completion -
Handover -
Move-in -

Tuesday, November 16, 2010

Bricks and Roof Tiles

Last week was a good week for progress. 

The bricks were completed, then on Thursday we saw the roof tiles delivered around 9am. 


I thought that probably middle of this week it will be completed.  Then when we visited the site last Saturday this is what we saw - a red roof!  


It looks like it is completed since most of the Finally I get to see how the brick and roof tile combo would look like and I couldn't be happier with what we chose.  We wanted to be a little different with our neighbors and yet a bit conservative in colour. 