Visited the site last Saturday to meet with the Electrical contractor only to be disappointed with what I saw - what they said that should have been fixed is still the same as a 1.5months ago.
But what's worse is that the contractor forgot about the sarking we have included in one of the amendments to our plans. It is part of the Basix report and we had added it despite of the cost for its additional benefit. I still don't know what will happen next but we really want those sarking installed.
I called the builder today and the customer service personnel is checking on it with the site supervisor. Even before this happened, I already requested that I inspect the property but I have not heard from them a schedule.
we call it Tahanan, a filipino word that means a house or home. A place to be at ease and feel the love of the family. Tahanan comes from the root word 'tahan' which means cessation of the crying or abolition of grief. It is said that your sadness goes away when you are in your own home.
Home Building 101
Our first home building adventure.
Tahanan Time Line
All about the land
Land Settlement (11-May-2009)
Land Title Transferred (25-June-2009)
Construction
Free quotation / Initial Tender
Security Payment
1st Draft of Drawing
2nd Draft of Drawing
Hydraulic Plan
Colour Selection
Final Drawing for Approval
Revision Requested by Certifier
Revised Drawing
Approved Plans via private certifier (24-March-2010)
Final Contract Review / Signing (21-April-2010)
Tree Removal (1-May-2010)
Submission of Letter to Commence Construction (9-May-2010)
Security Payment
1st Draft of Drawing
2nd Draft of Drawing
Hydraulic Plan
Colour Selection
Final Drawing for Approval
Revision Requested by Certifier
Revised Drawing
Approved Plans via private certifier (24-March-2010)
Final Contract Review / Signing (21-April-2010)
Tree Removal (1-May-2010)
Submission of Letter to Commence Construction (9-May-2010)
Drawings Revision Required (22-29 May 2010)
Rev2 drawings sent to the Private Certifier (24-June-2010)
2nd revision of the plan approved by Private Certifier (30-June-2010)
Day 1 - Construction (11-June-2010 ??, within 28 days) - 12-July-2010
Piering - 28-July-2010
Slab - 16-August-2010
Frame - 23-Sept-2010
Day 1 - Construction (11-June-2010 ??, within 28 days) - 12-July-2010
Piering - 28-July-2010
Slab - 16-August-2010
Frame - 23-Sept-2010
Brickwork - 10-Nov-2010
Roof Tiles - 12-Nov-2010
Lock Up - 16-Feb-2011
Fixing Out -4-March-2011
Painting - 8-April-2011
Lock Up - 16-Feb-2011
Fixing Out -4-March-2011
Painting - 8-April-2011
Final Inspection 13-April-2011
Completion -
Handover -
Move-in -